Project Info:
Owner:
Schnitzer Northeast

Technology:
Structural Steel and Miscellaneous Metals

Engineer:
Waldron Engineering

Project Value:
Confidential

Project Highlights:
The steel was specially fabricated and installed to accommodate the huge 10,000 HP Riverside Engineering M-122 Mega Shredder.


Download Project PDF

Everett, MA - Schnitzer Metal Processing Facility

The fabrication for this new steel shredder facility required detailed planning, scheduling, and installation by Summit Metal Fabricators. This was especially true regarding the installation and support of a Riverside Engineering 10,000 HP M-122 Mega Shredder. The enormous size and weight of the M-122 demanded that the steel support structure be of the highest quality and precisely executed. The work had to be fabricated and installed under an accelerated schedule in order to support the delivery and installation of the new shredder equipment, support framing, and conveyor systems.